Auto-Schedule based on just dependencies - Advanced Roadmap

Krishna Pandey
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 19, 2021

Hi,

I am using Jira Server 3.29.0 and I am looking to build a simplified Gantt view of my project based on dependencies. We are not a very tech heavy team so adding 'estimates' to the tickets is not something that we do normally.

Example:

1. Ticket A starts on 22nd Nov 2021 (Target Start Date) and ends on 3rd Dec 2021 (Due Date)

2. Ticket B starts on 6th Dec 2021 (Target Start Date) and ends on 17th Dec 2021 (Due Date)

3. Ticket A Blocks Ticket B i.e. they are sequential tasks (Ticket A to complete for Ticket B to start)

Now lets say at 25th Nov 2021, Ticket A's due date is pushed to 8th Dec 2021.  Because of the blocking dependency, this will be shown with a warning in Advanced Roadmaps. 

Desired Outcome: When I press 'Auto-Schedule', i would ideally want Ticket B to now have the target start date of 9th Dec 2021 and the end date of 22nd Dec 2021

 

Is this achievable?

1 answer

0 votes
Krishna Pandey
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 22, 2021

anyone?