Attribute Sub Tasks to Sprints

Jimmy Kim
Contributor
November 27, 2023

Is there a way that I can attribute sub tasks to a specific sprint? It looks like the lowest level that I'm able to attribute sprints to are at the Task level but not at the Sub Task. I have a bunch of sub tasks that I am trying to attribute to a sprint.

1 answer

0 votes
Trudy Claspill
Community Champion
November 27, 2023

Hello @Jimmy Kim 

In Jira, subtasks are not attributed to sprints individually. They move with their parent issue into and out of sprints. If you assign the parent issue to a sprint, then all of its subtasks go with it.

If that doesn't suit your need, can you explain more about your use case and what you are trying to accomplish?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 27, 2023

It is important to understand that sub-tasks are not sprint items, they are pieces of sprint items.  It is nonsense to have sub-tasks in different sprints, they are in a sprint because they are part of a story that is in a sprint.

Jimmy Kim
Contributor
November 27, 2023

Gotcha - that helps. It looks like the sub tasks were incorrectly classified as sub tasks and should have been tasks so they could be associated to a sprint. It's good to know that sub tasks cannot be allocated to a specific sprint.