The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

Are you able to reduce remaining effort to 0 when status = Resolved?

Peter Alouche
Contributor
March 29, 2021

Hello. We have been training remaining effort by considering work logged by both development and QC. To represent our development progress when the status is Resolved. Our developers have had issues with trying to change the remaining effort to 0 when the status is Resolved. Does anyone know why that is?  Is there a configuration that we can perform to workaround this issue?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Walter Buggenhout
Community Champion
March 29, 2021

Hi @Peter Alouche,

In the workflow of a company managed (classic) project, you could add a post function to the transition to status resolved. That would be an update issue field post function that would set the value of remaining estimate to 0. In the workflow, that would look like this (first line in the table below):

Screenshot 2021-03-29 at 16.31.10.png

Similarly, through automation you can do the same. Your automation rule would look somewhat like this:

Screenshot 2021-03-29 at 16.27.01.png 

Peter Alouche
Contributor
March 29, 2021

Awesome! Thanks @Walter Buggenhout !