All of my done issues are still 'incomplete'

Dusty Hansen
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 11, 2025

I just closed out my sprint and all of my issues marked 'done' are still showing as 'incomplete' and were moved to the next sprint.

I did add a new complete status of 'canceled' this sprint in the workfow. But all of my done issues are marked with a green checkmark and the 'done' status is in the done category.

I can't figure out what the problem is.

2 answers

1 accepted

4 votes
Answer accepted
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 11, 2025

Hi @Dusty Hansen 

Welcome to the community.

Is the "Done" status in the last column of the Spring Board?

If it's not the issues are not concerned done in the sprint and therefor not seen as complete.

Also see this KB article; done-or-resolved-issues-are-still-shown-as-incomplete-when-closing-sprints 

Dusty Hansen
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 11, 2025

I moved the column to the far right, but it didn't seem to "fix" my issue. Is there any way to fix the closed sprint? It has no completed issues in it basically, so it is throwing everything off.

Dusty Hansen
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 11, 2025

Nevermind, I was able to repopen the sprint and close it again. Thanks for the help!

2 votes
Anandhi Arumugam _Cprime_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 11, 2025

Hey @Dusty Hansen Welcome to the community!

Is there a resolution set on those issues? Check your workflow to ensure that the resolution is set as Done. Otherwise, the issues will be considered as Unresolved even if they are in Done status. So need to ensure that the issue is Done and the resolution is also set as Done.

Hope this helps!

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events