Advanced Roadmaps - Assigning teams (Capacity Planning)

Nanees Ibrahim
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 2, 2022

Hello, 

I'd like to confirm if the below feature is available when using the JIRA Advanced Roadmaps please. 

Is it possible to have 3 different teams within the same project, sharing the same sprint but working on different subtasks? 
If yes, how it is possible to view the capacity when planning a sprint per team? 

 

Thanks in advance.

1 answer

0 votes
Ste Wright
Community Champion
January 14, 2023

Hi @Nanees Ibrahim 

You can have 3 different Teams working within the same Project.

However, different Teams cannot own Sub-tasks under the same parent. The Sub-task inherits the "Team" from the parent (eg. Story, Bug, etc). This is because Sub-tasks are designed to be a part of the parent Issue, not a separate Issue.

You can have different teams own standard Issue Types though - eg. Story, Task, etc.