Add new lines in burndown chart

Joep de Hoon
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 11, 2021

Good day,

 

I have a question related to the burn down chart.

I have added seperate column on the Sprint Board: To do, Active, Dev Ready, Test Ready and Done (DoD).

The user stories will go trough this flow during the sprint.

Is it possible to add these lines in one burn down chart (Dev ready, Test ready)?

 

Happy to hear from you.

 

Thanks! Joep

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 11, 2021

Welcome to the community!

No, because they're not burn-downs.  You burn down an issue's estimate when the issue is done, not at other points in its life-cycle.  You would also have a problem with the lines in that they would go back up as the issue moves - that would really never make it look like a burn-down at all.

What you're asking for here is nothing like a burn-down chart.  I'd recommend you look at a cumulative flow chart or control chart instead, they will show you more about issues cycling through status during a period!