Hello Community =)
We're looking for the possibility while adding "Gantt Sub-Task" in BigPicture (Box/Program), to add automatically a pre-defined Link-Type as relationship between the issues.
UseCase:
Any suggestions how to solve it?
Many thanks in advance!
Danny
Unfortunately, it is impossible to make BigPicture add a link to a created sub-task automatically. Please note that this could cause a number of confusions, especially concerning the number of links available in Jira by default, not to mention custom ones created by Jira administrators in their instances.
That being said, I recommend that you fill in the 'Linked Issues' section upon the Sub-Task creation in BigPicture. This ensures that a correct link is selected between the respective issues. Please see the screenshot below for reference.
I hope that this clarifies. If not, please do not hesitate to ask more questions here or to raise a ticket via our Service Desk
Best regards,
Mateusz Sołowianiuk
SoftwarePlant Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.