I currently do not have access to the control chart option in Jira Reports (I can only see the following: Burnup report, Sprint burndown report, Velocity report, Cumulative flow diagram, cycle time report and, Deployment frequency report).
What do I need to do to a) get access to this report or b) build my own dashboard or report that will give me the same information?
Hello @Sharon Bond
Welcome to the community.
From the list of reports you specified, it sounds like you are using a Team Managed project (vs. a Company Managed project). It will say this at the bottom of the navigation pane on the left.
The Control Chart is available only in Company Managed Software projects at this time.
Here is the change request to add the report to Team Managed projects. You can vote and comment on it.
https://jira.atlassian.com/browse/JSWCLOUD-20651
I saw a response on this post from a person who indicated there is a third party product that can provide such a report for Team Managed projects.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.