The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Ability to set Work Estimate for burndown in Project Task tickets

Jig Bhakta
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 25, 2022

I understand that we can add Work Estimates to the main JIRA tickets but is this also possible for the Project Task issue type (Sub-Tasks)?

I have many JIRA tickets that have their work broken down into Project Tasks but I can't find where I can then add work estimates to those Project Tasks.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Karim ABO HASHISH
Community Champion
October 25, 2022

Yes it's possible as you see below, if you are a project admin, and the issue type subtasks are using a different set of screens than the task, you can simply add the field "Time tracking" to subtasks' screensUntitled.png

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 26, 2022

Please remember that sprint (and kanban) estimates do not go on to sub-tasks.