Hi folks,
I have an issue with a rogue sprint that made it into my release burndown chart but it shouldn't be there. Is there any way to exclude a sprint? What drives the sprints that are included here?
A bit about our jira config, We are using on Jira project for a number of mobile app and tablet related changes- this our product backlog. I use a custom field to create different boards based on change request ID, so the different pods only see the work that's relevant for their team. The other team's sprints are not populating on my release burndown as their stories are not included in the release (fix version) that my team are working towards. It's just the one stray sprint (CA Sprint 8) that somehow made it in and I can't seem to figure out why.
Any suggestions much appreciated!
Thanks,
Reka
I found a solution in case anyone else is in the same shoes.
I rogue sprint was in this release burndown because a story from this release was added to that sprint (by error).
Thanks,
Reka
What drives the sprints that are included here?
Typically you will get rogue sprints, when the scrum board filter of your team shares issues with a scrum board filter of an other team, e.g. when you have overlapping filters or work on the same release.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Leonard,
Thank you for your answer.
The driver of the sprints should be the release ie the fix version, in this case Overdrafts phase 1. One of the stories from this fix version was accidentally pulled into a sprint by another team (not sure how this happened). My worry is that on the release burndown, the metrics of this rogue sprint show as: 312 at start of sprint, 51 added to version, 78 completed and 285 remaining - but if I open the rogue sprint, CA sprint 8, it contains only one issue, the one from my fix version. I'm just trying to understand if I should exclude these figures from my calculation or are the figures correct (ie this is what actually happened in that fix version, during that time period)? What are the 78 story points that burnt down? Is there a way to open the issues that are included in this calculation (when I click on the bars on the release version)?
Sorry for the convoluted question, trying to make sense of it all.
Reka
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.