how can i track the percentage of completion of an epic in Jira next gen?

Luca Orciuolo
July 10, 2019

Hello,

I would like to know if there's an add-on or else that can help me to track the percentage of completion of an epic (I don't mind about stories and sub tasks).

I would like to manage the progresses of epics and transfer it to excel automatically while keep tracking and working on my project in Jira next gen.

hope you can help me, thank you

2 answers

1 accepted

0 votes
Answer accepted
Eirik Midttun
Contributor
June 22, 2014

You need to configure the agile board: Go to the Agile view, Board (upper-right corner) -> Configure. Then set Estimation to Original Time Estimate. This will however affect all users, it does not only concern your gadget. I do not think there is a way to set this only in the gadget.

https://confluence.atlassian.com/display/AGILE063/Configuring+Estimation+and+Tracking

Aamer Inam: M-3521
June 23, 2014

Hi Eirik , I have found out the estimation setting from board configuration . The second part of my question is how to view resource wise burn down charts e.g. if there are 10 stories , each assigned to a different resource .How can i view resource wise burn down of the same sprint .Look forward to your kind response. Thanks.

Eirik Midttun
Contributor
June 23, 2014

I don't think, or even hope, that this is possible. The burndown chart wasn't created to track individual progress, but that of a team.

Dave F
Contributor
July 28, 2019

I agree with Eirik there. Agile is about the goals of the team, not the individual. 

0 votes
Aamer Inam: M-3521
June 22, 2014

Also , please suggest that how can we view user wise burn down charts .