Hi,
Is there a way to connect changes made in WBS Gantt-Chart to the issues? Jira tasks of any type can be edited within the WBS Gantt-Chart view but they are not connected to the actual Jira issue. If you edited the name and then you open the Jira issue, the name and other information like that the start date, end date, due date, etc is not updated. Which means that the Road Map and the Gantt do not contain the same information.
The edit function should be connected in both apps.