Is there a way to change how different statuses on the board impact the progress bar on the roadmap?

Mike Nowak
October 23, 2019

For our workflow I would really like the right most columns "Ready to deploy" and "done" to count as done. Often times the only reason something wouldn't get deployed to Prod is because of some other business reason. For our purposes of calculating our velocity we'd like to be able to count things that are ready to deploy as done in the epic roadmap progress bar. 

1 answer

0 votes
mwarton
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 7, 2014

Hi Allison,

I have spent some time looking into the standard JIRA reports, and it is certainly not obvious as to what they do.

I have created sample reports for Intelligent Reports that follow the User and Version workload reports as closely as possible, but have not looked at the time tracking report.

Generally they seem to follow JQL queries along the lines of:

assignee={User} and resolved is EMPTY and (timespent > 0 or originalEstimate > 0)

and use timeSpent + remainingEstimate instead of originalEstimate.

If you need better control over exactly what gets reported, give Intelligen Reports a try. It lets you design the report in Microsoft Word, and fill in the data using simple point and click rules, no scripting or API to learn.

Cheers,