You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
We often have stories that need to precede or succeed other stories, is there a way to set up links that we can say that a story precedes another (the inverse would be that the second story succeeds the first one)?
I used to do this in Jira classic, although I don't know if that was through an add-in or not.
The list of types of links is set by your administrators. There's a default list in a new Jira install, but you can add to, remove or edit the whole list.
I would guess that your admins on your older Jira had set up a link type called something like "dependency" and then labelled the directions as "predecessor" and "successor". That's quite a common way to do it in my experience (there are more complex schemes with four types of dependency rather than two).
It may also have been provided by an app, there are quite a few that add their own link types like these, or implement their own link system and then layer more functions on top of their link systems.
I'd start with the simple built-in issue links and see if they do enough of what you need.