I created a project with Epics and tasks, each epic and task within have been assigned a due date. Our team has decided not to do Sprints but would like to see progress within each Epic to resemble a Gantt chart, how do I make reports when not using sprints?
If you would be interested in a third party add-on, you can try out Agile Tools, to track progress of issues in Epic hierarchy on time estimates and at story points as well.
Agile Tools - Epic Tree and Time in Status
The add-on allows you to manage and visualize multiple Epics hierarchy on a single page. Also add-on provides a hierarchy of a single Epic on Epic Issue screen.
Key features of Epic Hierarchy:
Along with Epic Sum, you also get 4 other important functionalities within the same plugin, Links Hierarchy and Multiple Time in Status reports (to track your issues), Worklogs Report and Timesheets
Thanks
Shaili
Hi, @Tracy Gallant. It's not necessary to use sprints to create some form of progress report. What is necessary is that your team is recording progress in some fashion -- e.g. story points completed or hours worked. And, that you have a way of showing that information, it sounds like you're looking for a visual way — like a Gantt chart.
Assuming your team is recording progress, there are a number of Gantt solutions for Jira Cloud you may wish to consider. One of them is Advanced Roadmaps from Atlassian (warning, it requires Jira Cloud Premium). However, there are a number of cost-effective, comparable solutions available on the Atlassian Marketplace.
Full disclosure: One of them, Structure + Structure.Gantt, is developed by ALM Works.
Hope this helps,
-dave [ALM Works]