You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
I may not be describing this accurately, but I'm a new administrator of Jira. My team has an existing next-gen project board and they want to add two workstreams or categories or components of work to the board. Similar to this screen shot that shows Expedite and Everything Else. How do I do this?
Hello, @Karen Martin
Select the Kanban Board -> Configuration-> Swimlane ->
There are 2 swimlanes which are already given in JIRA that you mentioned as per screenshot which you need to enable.
1. Expedite : priority = highest (This will show all the task with highest priority)
2. everything else : This will show all the task other than highest priority.
Note - You can make customized swimlanes as per your requirement in the same setting.