Hi Guys,
I am using GreenHopper with JIRA and I am using "Estimate Hours" for planning (no Story points), so as Scrum Master, I need to see some View with "Assigned Time" for every user in the "Current Sprint". Anybody can help me?
Thanks so much
Hi Francisco,
I noticed you mentioned that you aren't leveraging Story points. In Greenhopper, story points are an important factor for estimation and tracking. Quite often, Scrum masters estimate tasks in Story Points, then track tasks using hours. With that, following is an excerpt from our documentation: "If you are using Story Points as your Tracking Statistic, then the Burndown Chart shows the Story Points per story (ie. stories burning down the Estimate Statistic are only burnt down on the graph as they are completed); whereas if you choose the Time-tracking option you are shown partial burndown (ie. the number of hours currently used and remaining each day)."
Configuring Estimation and Tracking
https://confluence.atlassian.com/display/GH/Configuring+Estimation+and+Tracking
Viewing the Velocity Chart
https://confluence.atlassian.com/display/GH/Viewing+the+Velocity+Chart
Please let me know if this information doesn't get you on the right path.
Cheers,
Jason | Atlassian