Changing the Estimate statistic from Original Estimate to Story points

Karthiga Sethuraj May 11, 2017

Hi,

Now we are in the middle of a sprint. We changed the Estimate Statistic to Story points from original estimate. So that the velocity chart will show the ratio of completed to commited stories. Previously it was showing the hours commited and completed. 

Also changed Time tracking to None from Remaining Estimate and Time spent.

After changing the configuration the 'Estimate' field for all the issues is now displayed as "Unestimated". Though it has story points already estimated on the issue. This is the case for the issues both in active sprint and backlog.

Can you please advise why the estimate field isn't automatically picking up the story points assigned to the issues ?

1 answer

0 votes
Andreas
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 7, 2017

Story point estimates are saved in a different field than time tracking estimates. Could it be that you populate the wrong fields with your story points?

Karthiga Sethuraj July 7, 2017

Hi Andreas, This is fixed already. Thanks for your reply though!