Can two users view the same "Planned Sprint"?

From what I understand, "Planned Sprints" are the issues in the Rapid Board (specifically the "Plan" view) which lie above the Sprint Marker, but the sprint is not Active yet.

Our Product Management team is looking to plan the Sprint, but when one member adds an item to the Planned Sprint, it doesn't updated the other team member's Planned Sprint in the Plan view.

Is it possible that when I add an issue to the Planned sprint, for them to see this updated?

1 answer

1 accepted

2 votes
Accepted answer

Hi Adam,

At the moment the sprint marker is entirely client side and so there isn't any way for this to be shared between team members. We do have a feature request that's being worked on that you can find at https://jira.atlassian.com/browse/GHS-5383. Please do vote on that issue to increase it's exposure. :)

Cheers,

Matt

Thanks for the response Matthew (although it wasn't the one I was hoping for). If the plan is to move the agile portion entirely to the "Rapid Board" view, this should be a higher priority as it makes it very difficult for teams to plan a sprint.

This is a feature that we'd very much like to see as well. We were briefly confounded when trying to plan our first sprint in Greenhopper.

Thanks John!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in United States

Topic Tuesday: What's your favorite topic?

Good morning All, Our goal is to get you into the habit of while enjoying your favorite morning drink you are checking the NOVA "space" for topics and comments. Your input is really needed and...

57 views 4 0
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you