Roadmap - sub task end dates don't update Epic

I enjoy the concept of a roadmap, a visual Epic view (we use Big Gantt for this today but often it's overkill). 

 

The issue:

  • Add start & due dates for an Epic
  • Add a child task and add a due date which is longer than the Epic's due date

Result - roadmap is not updated.

Ideally the roadmap would show this extension, perhaps in a different color denoting that something is now stretching out after the intended due date.

2 answers

There is light weight, and there is completely useless.

If there is no indication of the due dates of child tasks at the epic level, then whats the point of setting a due date on an epic anyway?

0 votes

Hi @Paul Steckler

Thanks for your feedback. 

Ideally, it makes sense that due dates of epic and its children should automatically adjust according to each other. But we also know that it's commonplace for different teams to have different definition of 'done' when it comes to epics (i.e. epics can be considered shipped or done without stories on final clean up completed). It also happens surprisingly often that a user would accidentally submit wrong due date for stories. 

Since roadmap is a new feature in its early stage, we kept it simple and light-weight. However, we'll be watching how teams are using roadmap and keeping your feedbacks close to heart to learn and iterate on the experience to make it smarter. 

If you're using epics and roadmap extensively with your team, we'd love to chat to you more about your experience. If interested, please fine some time here

Cheers,

Erika Sa

Atlassian product manager

Thanks for the response Erika.

With the new Agile template being kept simple, which we **really** like, roadmap as a purely manual construct simply won't scale to where we need it to be without some amount of aggregation in Due Date.

Our outline looks like this:

  1. Epic - The big, often 6 month long work item.
    1. Story 1 - aerial collection (we fly airplanes and build maps)
    2. Story 2 - processing of incoming data.
    3. Story 3 - delivery to customers

In traditional Gantt and such these would truly, for the most part, waterfall (sorry agile people, this is the world we have). For visualization either a) we set a Due Date on the Epic. Or the _latest_ Due Date of a child pushes the roadmap item out. 

We don't need the big complexity (we use Big Gantt plugin today which is brings it's own set of issues) but without some form of roll-up then roadmap is more or less just a bunch of pretty lozenges we have to deal with manually.

 

We have ~200 Epics at any given moment to track and report on.

Erika Sa Atlassian Team Oct 02, 2018

Thanks for providing more context @Paul Steckler, this is very helpful. We'll take this into account for future iteration.

In the meantime, could you tell us a bit more about the report you do on ~200 epics? What does it look like today  and what should it look like in an ideal world? 

Erika - give me a shout directly and I'm happy to walk you through the labyrinth :-)

The data is fairly confidential so better if we could screen share perhaps. I can also show you a) ideal, b) less than ideal, c) Smartsheet version, and d) where we'd like to wind up. Tricky project (they all say that I'm sure).

Erika Sa Atlassian Team Oct 02, 2018

Not sure how to message you directly here @Paul Steckler but feel free to email me directly to esa@atlassian.com or book some time with me here

I agree with Paul.  There has to be some kind of of date-related link between the roadmap/gantt (which is a visual representation of the date range) and the associated stories and tasks.  Otherwise it is misleading, giving the impression that all the related work will be done in that timeframe. 

At a minimum, there should be some kind of warning on stories/tasks that fall outside the epic date range and/or some indication on the roadmap that there are associated stories/tasks that fall outside the time range.

Like # people like this

Completely agree with @Steve Lanaghen. I really appreciate the Roadmap feature, but I do also really miss the connection between start- enddate of a roadmap epic and it's child issues. 

My backlog can be prioritized completely different than my roadmap visually represents, and there's nothing restricting me to adhere to that planning. 

I totally agree with Paul. 

Roadmap is a really cool (and useful) feature, but done update the EPIC due date based in child tasks due due date is painful.

Total agree with Paul. It should be automated.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Next-gen

Keyboard shortcuts have arrived for next-gen projects!

...ollected feedback from users around the lack of shortcuts, and we’re here to address that: In next-gen projects, I miss the keyboard shortcuts badly. This is particularly true on the Board, but also i...

221 views 2 4
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you