after stories are completed and we generate a sprint report, some issues are starred.
Why?

Screen Shot 2019-11-04 at 9.27.55 AM.png

1 answer

1 accepted

0 votes
Answer accepted

Hello @Efoe Adjakly,

Welcome to Atlassian Community!

The star symbol in those issues (*) means that the issues were added after the beginning of the sprint, as described in the "Understanding the Sprint report" section of this documentation:

Issues added after the sprint starts are indicated with an asterisk.

This feature is used to better display for you the amount of work that was not initially planned for that Sprint.

Let me know if you still have any questions about this.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published in Jira

The add-in you’ve been waiting for: Jira Cloud for Excel 🙌

Introducing Jira Cloud for Excel Here at the product integrations team at Atlassian, we are thrilled to announce the new Jira Cloud for Excel add-in! This add-in lets you export Jira data directly ...

966 views 9 25
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you