You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
we are unable to add Multiple values under the sprint. can you please help us the reason. how to be able to add.
@Thokala Suneetha If you are using parallel sprints, make sure this global setting is enabled.
Hello @Thokala Suneetha
An issue can be in only one Active or Planned sprint at a time. That is why you can't select multiple sprints in the Sprint field for a given issue.
By setting the Sprint field you are assigning that issue to that sprint. In the agile methodology you are making a commitment to complete that issue during that sprint. If it isn't completed within that sprint, then when you close the Sprint you can move that issue to another active or planned sprint or put it back into the Backlog.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you are using Default Field offered by Jira, then you should be able to select multiple sprints in the same sprint field.