is there anyway to handle stories covering over multiple sprints ?

Shamith Shankar January 24, 2017

we are tracking Epic as a bigger project and stories as features, since stories is same level as tasks . stories which cannot be closed in 1 sprint , but wants to show the amount of work done in that sprint . is there any way to do it other than breaking the stories into smaller ones ? i think sub-tasks will take same sprint as its parent, right ?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 24, 2017

The usual response to this is yes, break your stories up (or, in some cases, make your sprints longer).

You are right, sub-tasks belong to a parent and hence are part of the story, so always in the same sprint.