Hi Community
I keep exploring Plans and Goals, and another pretty logical piece seems to be missing.
In the list view of Timeline, I can see the status of an Epic alongside its Start and end dates, but I would be super happy to see the progress bar for Child issues.
Progress in days is kind of useless for us, as we don't use estimates, and I want to focus on work done first not in days (for days Start date and Due date are perfect)
So far, I haven't found a way to achieve this.
picture 1: where I would like to see the progress bar
Picture 2, the progress bar that I am missing
I would appreciate any hints, as overall, the Goals and Plans look very promising, but these "little missing things" are killing all the positive effects (especially because we will need to switch to Premium, which will require a budget, and it is hard to get when we have such apparent things missing)
Welcome to the community !!
If you would be interested in an add-on for this need, you can try out our plugin.
The app shows your issue hierarchy in a tree view and the ability to add all your jira columns in the report, plus you will be add the app as a dashboard gadget too.
The screenshot below is the issue view screen which is another feature the app provides.
The app has multiple other features which are very useful in project tracking and management.
(Disclaimer: I work on RVS, the vendor for this app)
thanks for sharing, will give it a try and let you know whether it is solving the core problem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have played with it, and it looks interesting, but I would like to get this in Plans.
Otherwise - I loose all the good things of that part of Jira world
As a result - for now - I disable the plugin, and keep digging to find better solution
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Vasiliy Ganchev ,
Are you the child issues on the sub-task level? Timeline doesn't visualize those. You have to upgrade to Advanced Roadmaps for that. Alternatively, you can use apps in the Marketplace to make roadmaps.
(Full disclosure, I work at Visor and we are one such app. Free to use: https://marketplace.atlassian.com/apps/1226209/visor-spreadsheet-gantt-chart-for-jira-with-excel-export?tab=overview)
I'm curious though if you're looking to visualize tasks or sub-tasks. If the former, you should be able to do that.
-- Becky @ Visor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Becky,
Thanks for looking at my post and sharing your advice!
The child issues that I am talking about are not on the sub-task level.
Regarding Advanced Roadmaps - actually, I am already on it (the first screenshot).
I will give a try to the app you shared and get back with a feedback
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Becky Brooks - Visor for Jira We're also looking for a way to show a progress bar of tasks within an epic on the Plan > Timeline view. Can you explain how to achieve this? I think it may only be possible on standard Timelines, not on the Plan > Timeline
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Actually, I found this other post helpful https://community.atlassian.com/t5/Advanced-planning-questions/Visualize-progress-of-epics-used-by-more-than-one-project/qaq-p/2397118 and used that to add a "Progress" field
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.