I want to remove the weekends, which are the days I don't work, from my timeline, to better define the deadlines for my activities, without adding more days that I won't be working on the project.
Hi @Ana Nobre
Welcome.
I expected you are referring to the board option Timeline.
If you are working in a Company managed project, on your board, select the 3 dots (top right hand) and configure the board.
Select working Days and choose the applicable days..
But I see what you mean, the days are still there in the timeline.
I don't think its possible to remove these in any way, this is built in.
Raise an issue at Atlassian Support if you need more information
Hi @Ana Nobre
Welcome to the community!
You can configure the working hours and days:
The documentation is here: Configuring working hours and days
It's also worth looking at the working days configured for your individual boards so the teams can see what's happening too. Read more here Configure working days
I hope this helps!
Best regards
Sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
this option seems to only exist in the cloud version, I am not seeing an option to configure working days in data center.
Am I missing something?
BR
Borris
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For server please check https://confluence.atlassian.com/jirasoftwareserver/configuring-working-days-938845342.html
Best regards
Sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Samuel Gatica (ServiceRocket)
thx for your answer.
I am not sure if I understand. Your link leads a documenation on agile board configuration. I understood that the inital question was about Advanced Roadmaps.
I also found this blogpost: https://community.atlassian.com/t5/Advanced-planning-articles/Ending-support-for-the-Advanced-Roadmaps-Live-plans-Legacy/ba-p/1963824
-> It mentions the removal of Weekday configuration in favour of agile planning
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It seems about Advanced Roadmaps by the mention of timeline, but is related to the board function "Time Line"
This can be used on Company Managed projects only and you can define working days
Plans (advanced roadmap) is useful for cross project, this function is for a single project only. And even only for the issues in the single project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.