I have a problem when I create new portfolio plan. No matter what I provide as data sources for the plan none of the epics are present in the plan.
For all the stories in the project, some of the epics are in the same project, some are in a different project.
I've tried:
Expected Result: I should see the epics with the stories nested under them in the wizard
Result: No epics appear in the plan, but they are all present on the board.
Expected Result: I should see the epics with the stories nested under them in the wizard
Result: No epics appear in the plan, but they are all present on the project and the filter.
Expected Result: I should see the epics with the stories nested under them in the plan
Result: No epics appear in the plan.
Expected result: after I commit the change of adding one epic to the plan it should appear in both the project and the plan
Result: Epic is created in the project but after commit is no longer present in the plan.
Actually this is from @Martin Suntinger via email, and is in reference to this other question I didn't find: https://answers.atlassian.com/questions/38390402
Our instance had the FixVersion field hidden for epics and that caused Portfolio for JIRA to not 'see' those issues at all because (from that Live Plans answer):
...like for example having removed the fixVersion field at all from the issues? Portfolio checks this field when loading issues to see if its in an included or excluded assignment, if the whole field is not there, it might cause problems
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.