cannot see timeline / how to set 'default filter to only show issues from 1 project'?

Bart
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 5, 2024

Basic user here on free plan. 

Created a 2nd project and now the timeline views disappeared in both projects with a message that I need to set a default filter to only show issues from each project. Why is this not the default - I guess since the alternative requires me to sign up for a paid plan (which is what is shown on a promo message on the page) so it is made more difficult to keep same functionality on a free plan...

Anyways, how do I do this exactly to see a timeline for each project that only shows the issues for each project? I read up on other posts here and it shows to create custom filter to show issues for a single project only on Kanban board. So I did that with 'project = <name of my project>'. I can select this custom filter on the board but do not see any 'Save' button so filter settings disappears when changing the page. Note that I created a sprint so I assume the board applies to the sprint.

Again this is needlessly difficult. Common sense would be for the default to show for each project only  issues of that project.

 

3 answers

2 accepted

2 votes
Answer accepted
Walter Buggenhout
Community Champion
October 6, 2024

Hi @Bart and welcome to the Community!

I am not sure what steps you have taken here, but it seems as if you have somehow created a board and used a filter as the source of this board instead of the project itself.

If you do create a new Jira project from an Atlassian template, this is not the default behaviour. A new project comes with a board limited to that project's scope and it shows the timeline by default - for the connected project. So I am quite sure you have done some manipulations that may not have been necessary, causing the behaviour you see.

Just a couple of things here:

  1. If you want a separate board for each project, with a separate timeline for that project only, that is perfectly possible on a free plan (and default behaviour when you create a new project). I'll resume this right away ...
  2. If you want to have a single board with issues from multiple projects, that is possible with a free plan too, but it does indeed disable the timeline feature. For timelines across multiple projects, you would need the advanced Plans feature from the premium plan.

Resuming the first case, I would assume you now have 2 Jira projects, each with its own board. Assuming these are company managed projects, each board has a board filter that you should be able to locate on the General tab of the board configuration.

If your first project was called Project A, do the following to fix your timeline:

  1. Locate the board associated with Project A
  2. Navigate to Configure Board > General
  3. Click Edit filter query where you see the board filter presented as JQL
  4. Update to Project = "Project A" ORDER BY Rank ASC (replace Project A with your real project's name obviously).
  5. Run the query in the issue navigator and click the blue Save filter link.
  6. Return to your board settings and check the Timeline tab to ensure this is enabled

After that, you should have a working timeline just for your project A. Repeat the same steps for project B.

Hope this helps!

0 votes
Answer accepted
Valerie Knapp
Community Champion
October 6, 2024

Hi , @Bart welcome to the Atlassian Community and thanks for your quest

I have a free plan in one of my instances and I was able to get the timeline to work. 

Please can you check your configuration? Basically the timeline is just another view of the board. 

markup_1000017873.png

Here I have a very simple board with a few issues

Then, when I go to "configure board", it should be possible to switch on the timeline view and to include children issues in the view or not

markup_1000017875.png

With this configuration, I can see the Epics and their linked Stories in the timeline

markup_1000017876.png

What is your configuration? How is it different?

0 votes
Bart
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 6, 2024

Valerie and Walter, thank you for the reply. 
I was able to do a workaround to solve the issue. I realized that the new peoject (project #2)  I had created was a team project using the Kanban template. The previous project I had (project #1) was a team project using the Scrum template. I created another project (project #3) again with the Scrum template instead and deleted #2. Now I see a timeline in #3. I still don’t see a timeline in #1 but since there is no more development on that, it’s not a big deal. 
So not sure what happened here as when I created #2 the timeline in #1 disappeared and was not able to see it for #2 either but in any case my immediate issue is resolved now. 

Valerie Knapp
Community Champion
October 6, 2024

Hi @Bart , I'm glad we were able to help. The instructions that @Walter Buggenhout gave about having a board where you can see issues from multiple projects is only valid for company-managed projects. Team-managed projects are basically like silos / allow for a standalone configuration but then can't really be accessed by other projects. 

Anyway, I hope you got what you needed but if you need more help please just ask 