Working hours per day = 7u36min instead of 8 hours

Rafik Bouizergane August 7, 2023

In Jira, 1 working day should be equal to 8 hours. We noticed that for some boards, 1 day = 7h36m. Does anyone have an idea how that is possible? 

2 answers

2 accepted

2 votes
Answer accepted
Utkarsh Singh
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 7, 2023

Hi @Rafik Bouizergane You have to make changes here-

Screenshot 2023-08-07 at 7.06.47 PM.png

Rafik Bouizergane August 7, 2023

It is already at 8h but for some boards a working day is 7h 36min I have no idea whyScreenshot 2023-08-07 at 15.41.19.png

Utkarsh Singh
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 7, 2023

Can you please share a couple of screenshots showing the same?

Utkarsh Singh
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 7, 2023

Hey @Rafik Bouizergane How did you solve that? :) 

Rafik Bouizergane August 7, 2023

Hi @Utkarsh Singh 

It went away on its own after rechecking.

Utkarsh Singh
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 7, 2023

Strange!!

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 8, 2023

Hi @Rafik Bouizergane 

That is strange...I wonder if someone else made a change.

How many people are organization or site admins for your Jira site?  Have you asked the other people about their recent changes and/or looked at the site audit log for changes?

Kind regards,
Bill

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 8, 2023

I've seen this before, it was all about clashing admins.

Default to 40h working week, an inexperienced admin didn't realise it was a global setting, and set it to a 35h week for a project.

Another project spotted it, but it flxed itself when the admin realised what he'd done, or anyone else noticed it!

Like # people like this
Rafik Bouizergane August 9, 2023

I checked and no one made any adjustments. So I don't know how that came about. But whatever, the problem is solved

0 votes
Answer accepted
Charlie Misonne
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 7, 2023

7h36m means a 38 hours work week.

Can you check the Time Tracking menu in your Jira's global settings?

There you can set the amount of working hours per day. I don't think it can be set at the board level.