Hi all,
I would like to measure predictability using story points and show the burndown in a dashboard, but the sprint burndown gadget shows me remain time estimate. DO you know why?
The user story has Story Points.
Thank you in advance
The reason the burndown chart is showing Time is because your board is configured to time as the estimation or the "Remaining Estimate and Time Spent" is selected. You can change that by going to Board settings > Estimation and change it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.