How do I connect the Start Date and End Date fields to the Road Map/Timeline in Advanced Roadmaps?
In the Jira Epic ticket, I inputted a Start Date. However, the start date is not auto-populating within Advanced Roadmaps.
Thank you!
Image 1:
Image 2:
Hi @Peter Yoon,
The start and end dates in your plan are based on custom fields you configure in your plan settings:
By default, these are Start date and Due date, but you can update those. Make sure to check you have configured the correct custom fields.
Two additional things: