When to manually set "Remaining time"?

When logging work, I see I can "reduce estimate" or "set" it. But how is that different from setting "Remaining" time? Is the only difference than no time is logged, just decreased (i.e. in case of clear overestimation)?

1 answer

Scrum totally relies on what is the actual remaining estimate rather that the original estimate (that was the way earlier project management used to work). The time spent on a issue is not a factor in deciding how much work is remaining in that issue. Which means, every time you log work, you are doing an estimate and putting that value manually in the remaining estimate.

mmh, if there is no remaining time, the time spend does not become visible as remaining time. The time spend reduces the remaining time.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Apr 17, 2018 in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

800 views 2 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you