When I log time in a subtask (hiearchy -1) does inclued it to the task above?

İclal Aslan
Contributor
November 26, 2024

Hi,

There are 3 hiearcy levels on our system 1,0,-1 

When I log time in the child issue (0) it shows on the parent issue (1).

When I log time in subtask (-1) does it alose shows on issue above(0)? thanks.

1 answer

1 accepted

3 votes
Answer accepted
Duc Thang TRAN
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 26, 2024

Hello @İclal Aslan 

In the parent issue (level 0), you have a checkbox ( Include subtasksthat lets you specify if you want to include logged time from subtask issues (level -1)

2024-11-26 09_33_20-[SDDAO-11749] Modification projet JIRA SPO - Jira — Mozilla Firefox.png

Hope this can help you :)

İclal Aslan
Contributor
November 26, 2024

Hello,

Thank you so much.

I am using this JMWE function to sum all the logged times to epic (1) and then copy the value to budget issue type.

Is this funsiton includes subtasks? Thanks.

Screenshot 2024-11-26 115944.png

İclal Aslan
Contributor
November 26, 2024

Also,

 

If you have any idea about if this would do the same job? Adding all the log's in epic even though the parent issue of the subtask is not directly epic?

Screenshot 2024-11-26 120233.png

Duc Thang TRAN
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 26, 2024

Hello @İclal Aslan 

I'm not expert of JMWE to provide you with good advice.

However, I can share my use case: I have two field scripts configured.

  • Σ Time Spent for Standardissue (Level 0) = time spent on this issue + the time spent on its subtasks
  • Total Time Spent for Epic  (Level 1) = Σ Time Spent of its child issues (Level 0)
  Hope others personnes can help you 



 

İclal Aslan
Contributor
November 26, 2024

Hello,

With this idea we can say that 0th level issue 's Σ Time Spent gives me 0 and -1 issue time spent. :)

Thanks!