Is there any particular setting needed so that the Prediction of Completion date in the Version Report can produce the prediction data?
Hi @Alfred Tan
On the documentation for this report: https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-version-report/
It describes:
10% of the estimated work for the version will need to be complete before the predictions can be calculated.