WBS Gantt-chart - scheme

Jana Mandulová January 11, 2023

In the app configuration there is a possibility to set up Gantt Scheme.

How do I assign a specific scheme to an existing gantt chart?

1 answer

1 accepted

0 votes
Answer accepted
Shin Asaba
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 11, 2023

In the app configuration there is a possibility to set up Gantt Scheme.

You can create a new Gantt scheme by following the steps below.

  1. Click on the gear icon (Jira administration) > Select Apps > Click Gantt Scheme from the left sidebar Gantt Scheme.png
  2. Click + Create Scheme Gantt Scheme 2.png

  3. Enter a Scheme name > Click Create Gantt Scheme 3.png

How do I assign a specific scheme to an existing gantt chart?

Please be advised that you can assign a specific Gantt scheme only when creating a new Gantt (See the below image for details.) Gantt Scheme 4.png

For more information about Gantt Scheme, please refer to the link below.

Gantt Scheme

I hope this helps to answer your question.

Jana Mandulová January 13, 2023

Thank you very much for your explanation.