Version Report shows issues in wrong Sprint

Richard Forsythe May 25, 2017

I am looking at the Version Report and it is showing a list of stories that were completed in each sprint.

Sprint 3

70

209

210

...etc...

However, issues 209 and 70 were closed during Sprint 2 not Sprint 3. The Sprint report shows the issues correctly, as does the Velocity Chart.

This issue seems to stem from when an issue is closed in the morning before a Sprint ends and a new sprint begins.

Why the inconsistency between reports?

[JIRA v7.1.6]

UPDATE: Further research showed this to be an anomaly that arises if two sprints are open simultaneously and you close a story that is still in the earlier sprint. Even though the story was NEVER moved to the new sprint, the Version Report uses the date/time stamp to assign the story to the later sprint. The other reports use the "Fixed Version" field to assign stories to Sprint.

This is still an odd discrepancy between the Version Report and other reports. 

1 answer

0 votes
Fabio Racobaldo _Herzum_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 6, 2024

Hi @Richard Forsythe ,

did u try to perform a project reindexing?

Fabio

Suggest an answer

Log in or Sign up to answer