Unable to see closed stories on portfolio plan

Namrata May 30, 2023

I wish to track epic progress. Actual progress is somewhere around 23% if i track on excel but on jira it is only 13% because it is not considering closed stories. How do I get exact percentage of completion if closed stories are not visible even though i have selected status as closed, to-do and in progress. 

 

Help me, it's urgent

2 answers

0 votes
Namrata June 1, 2023

Resolved after including Resolution field. Thank you.

0 votes
Florian Bonniec
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 30, 2023

Hi @Namrata 

 

Are the closed story using a status that have Done status category ? Also have you set a resolution when a story is closed ?

 

Regards

Wesley Payne May 30, 2023

Hi Florian, 

 

I hope you are doing well.

I work with Namrata, so the workflow ends with a closed column and closed "status". i just noticed that their is no resolution field on the screen scheme.

 

If i add that field to the screen scheme and it is captured would that assist with the above? 