I wish to track epic progress. Actual progress is somewhere around 23% if i track on excel but on jira it is only 13% because it is not considering closed stories. How do I get exact percentage of completion if closed stories are not visible even though i have selected status as closed, to-do and in progress.
Help me, it's urgent
Hi @Namrata
Are the closed story using a status that have Done status category ? Also have you set a resolution when a story is closed ?
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Florian,
I hope you are doing well.
I work with Namrata, so the workflow ends with a closed column and closed "status". i just noticed that their is no resolution field on the screen scheme.
If i add that field to the screen scheme and it is captured would that assist with the above?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.