Unable to close existing sprint forgot to close first sprint0 and now sprint1 is in progress

Bineet Kumar Jha May 22, 2023

"By mistake I forgot to close previous sprint. In Jira board for LP360, currently there are 2 active sprints so, I am not getting close sprint option. Please help me & close my previous sprint - Sprint 0"LP360 Sprint issue.jpg

1 answer

0 votes
Vikrant Yadav
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 22, 2023

Hi @Bineet Kumar Jha Welcome to Atlassian Community!

Go to Active Sprint on your project sidebar >> select the sprint you want to complete from the sprint drop-down>> Click Complete Sprint.

Suggest an answer

Log in or Sign up to answer