Dear Community,
I use the Timeline view in my Jira board. I can adjust “Start Date” and “Due Date” in all of my tickets, but in timeline only the Epics issue type has a visualization of this time frame. If I search in the www then I found some picture where it is also usable for other tickets like tasks here.
Is this a bug can I adjust it somewhere or is this the feature?
Thank you for your response.
Hello @Michael Ohme
Welcome to the community.
There are different Timeline features in Jira Cloud.
One is the timeline available with Jira Work Management (a.k.a. Business) projects. That is the one referenced in the link you provided.
The other is part of Advanced Roadmaps (for Software projects) that is available only in the Jira Cloud Premium subscription.
Or you may be working with a third party app added to your system that presents a Timeline feature.
To which one are you referring?
Hi Trudy,
thank you for your response. I guess it is the "normal" timeline for software projects.
We don't have a premium or enterprise account, I guess. Where can I see it? In my backend was no information available. Perhaps I have not all permissions.
It looks also not like a plugin. If I click at "project settings" in the left bottom side of the menu bar, then at "Features", I have the possibility to activate/deactivate it.
Kind regards Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You would need Jira Site Administration access to check the licensing for your Jira Cloud instance to find out if you have the Standard or Premium plan. You could check with your Jira Administrators to see if they have access to that information and to confirm if they have installed a third party app that is providing the Roadmap functionality.
In the Standard Jira Cloud plan I believe that only the time range for Epics will show in the Gantt chart in Roadmaps. I don't use the Roadmaps feature, but that is what my experimentation revealed.
Does your screen actually say "Timeline" on it, or does it say "Roadmap"? Can you show us a full screen image (blurring any sensitive data)?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Trudy,
again, thanks for your time! I have admin permission in our Jira ;-) and it is a question of my colleagues, I can not solve with my skills.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Michael,
Based on the image you provided you appear to have the Jira Standard subscription. In that case, time bars are available only for the Epic issue types in the native Roadmap feature for Jira Software projects.
To get time bars for issues that are children of Epics you would need to upgrade to the Jira Premium subscription or look at a third party product for managing your roadmap/timeline.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Trudy,
thank you for your answer. Then I can stop wasting my time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone,
I have the same issue with the now called Time Line (not Plan) feature. But I have an enterprise subscription. Epics does show a bar, task not.
What can I do?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Robby Klee
The only people who have seen your addition to this Question that is over 2 years old are the original author and people who responded to it.
To ensure your question is seen by a wider Community audience, please start a new Question post. If you think this old post is relevant then include a link to it in your new Question.
It would also be helpful if you provide additional information, like the type of project and board with which you are working, and screen images of the Timeline and the issues involved.