I have created a Kanban project for my IT project. I have a few tasks which take ony 2 days but the blocks on the timeline bar can only be dragged to a minimum of 5 days. Smaller is not possible. If I go into the task I can set the start date and end date so it shows two days, so that's a workaround. It would be easier though if I could drag the timeline bar to two days so I don't have to manually type it. Is there any way to do this? Is there any reason why it has a minimum of 5 days on the timeline?
Thanks,
Wim
Hi @Wim Stylemn and welcome to the Community!
You can drag the timeline to a smaller number of days if you switch the timeline to week view near the bottom right of your screen.
I suppose this is a design choice (not taking any stand on if this is the right choice or not), as it probably becomes difficult to extend the schedule bars to the left or the right if they become too small in month view.
Hope this helps!
Oh ok, super. That's it indeed. Thanks a lot for the help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You're welcome, @Wim Stylemn! If my answer was helpful, consider marking it as an accepted answer. That makes it easier to find for people looking for similar solutions!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.