3 votes

Hi Judith, if there are epics in the backlog, but they don't show up in the schedule, it means the scheduling algorithm could not determine a possible timeline for these epics. Reasons could be: 

  • The epics don't have an estimate (an epic can have an estimate by itself while it has no child stories, otherwise it is the total estimate of the child stories)
  • There are no resources available who can be assigned with the epics (e.g. no teams/team members are defined or insufficient team velocity to fit anything in)

Typically, if the epics cannot be scheduled, they are highlighted in red in the backlog table after pressing "Recalculate", and when hovering over the items title (the first column), there is a tooltip giving more details on why it could not be scheduled. 

 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 16, 2018 in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

77 views 0 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you