Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Target start and target end (date fields from Portfolio) treated as empty fields even they are not

Running JQL:

"Target start" is empty

Expected result:
Only issues where the Target end-field is empty

Actual result:

Issues with target end date is also included

 

Anyone else experiencing the same issue with the date fields from Portfolio for Jira?

 

2 answers

1 accepted

0 votes
Answer accepted

I experienced this exact same problem a couple of days ago.  A re-index of the individual project cured it for me.  I would suggest a full system re-index if you are able to do that.

Reindex solved it. Thanks

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you