Swimlane in Timeline

Stefano De Santis February 26, 2025

Hello,

Is it possible to add a swimlane based on Components in the Timeline of a Project? Or add a column or a reference of Components in the Timeline (now there is the explicitation of Sprints and Releases.

Thank you

1 answer

1 accepted

1 vote
Answer accepted
Tomislav Tobijas _Koios_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 26, 2025

Hi @Stefano De Santis ,

In the project timeline that's not possible. However, if you would use Jira Plans (formerly Advanced Roadmaps) then the option to group issues by Components is possible.

2025-02-26_12-34-59.png

Configuring Timeline in the project is relatively limited as there's this 'more advanced' version of timelines/Jira Plans.

Cheers,
Tobi