Sub tasks do not have a value for the 'Estimate' field error while starting the sprint

Aswani kumari
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 15, 2023

I am unable to start  the sprint, getting the below error.

Issues subtasks do not have a value for the 'Estimate' field. Values entered after the start of the sprint will be treated as scope change.

Includes issue(s) currently hidden by a Quick Filter or the Instant Filter.

Please help

2 answers

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 15, 2023

Welcome to the Atlassian Community!

One of your admins has set the estimate field as mandatory, but not added it to the create screen.

This is not a good thing to do - you should not be putting (sprint) estimates on sub-tasks unless you have automated a system to calculate them up to the sprint items in a way that won't break all your reporting (most people don't understand the initial double counting, but then try to implement a scheme that ruins your team's ability to be Agile)

So, the best thing you can do for now is removing the field from sub-tasks and make it optional.

Then you can look at how you really want to do estimates.

0 votes
John Funk
Community Champion
March 15, 2023

Hi Awani - Welcome to the Atlassian Community!

it sounds like someone has made that field mandatory for sub tasks. you should check the field configuration for the sub task issue type to see if that is the case.

Suggest an answer