Structure - How to output a calculated value within a wiki markup panel

Johanna Leopold December 17, 2021

Hello,

I would like to display a formula with wiki-markup panels, but instead of returning "due soon", "overdue" etc. I want to return the days from now until due date.

It allows me to use "DAYS_BETWEEN(Today(), DueDate)" (without wiki markup) to show the days until a task is due or the following markup formula:

IF (dueDate < today(), "{panel:bgColor=red}Overdue{panel}",
DAYS_BETWEEN(today(), DueDate) <= 7, "{panel:bgColor=orange}Due Soon{panel}",
DAYS_BETWEEN(today(), DueDate) > 7, "{panel:bgColor=lightgreen}Due Later{panel}",
"")

What I would like to achieve is the first (number of days) within the coloured panels, but it fails to add calculations (or even variables, I tried with simply the due date). 

Is this even possible?

1 answer

1 accepted

5 votes
Answer accepted
Johanna Leopold December 17, 2021

Update: After posting, it showed me https://community.atlassian.com/t5/Jira-questions/Formula-Column-change-color-of-the-value-calculated/qaq-p/1750811 as related and CONCAT solved my problem!

Dave Rosenlund
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 17, 2021

Thanks for sharing your self-discovered answer with the community, Johanna! :) 

-dave 