Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,559,096
Community Members
 
Community Events
184
Community Groups

Standard roadmap does not show all sprint

From this topic here

https://support.atlassian.com/jira-software-cloud/docs/customize-your-view-on-the-roadmap/

We understand that all of the sprints will show up under the roadmap but it isn't. Every month we have two different sprints for each smaller team(TSO and SIS). When we enable the roadmap feature, only the SIS sprint has shown on the roadmap schedule, TSO's sprint doesn't. 

Sprints that have both start and end dates, and are associated with the board will be listed at the top of the roadmap, along with the months

Do you know what it means?

  1. Schedule bars: Each bar represents how long your tasks are scheduled to take. The sprints associated with the board are listed at the top of the roadmap along with the months. To see the exact dates of an epic, hover over its schedule bar. Sprints that have both start and end dates, and are associated with the board will be listed at the top of the roadmap, along with the months.

5 answers

Same issue here, one board is showing it, not the other, identical setups.

 

Looks like a bug

Need help on this as well

Yep - I guess this is a bug. Hey Jira! Any comments here?

We encountered this issue and found that deleting the sprint and recreating it helped.

0 votes
Jacob Vu
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 25, 2021

Hi @Pham Van Hung

Are they associated with the same board and do they both have the same start and end dates?

J

Hi @Jacob Vu 

Yes, they are associated with the same board. The start and end dates will be different, Do we have to put the same date for those sprints? 

Thanks, 

D-12_Admin_-_Roadmap_-_JIRA.png

I don't see my sprints displayed either they are like the picture above, My sprints have dates entered.  Do I have to associate my epic to the sprint?  My child tickets are associated to the sprints

Markus K
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
Feb 22, 2023

hi all, any updates on this one?

jamiot-ww
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
Feb 24, 2023

https://community.atlassian.com/t5/Jira-questions/How-to-show-sprints-on-the-timeframe-markers-of-roadmap/qaq-p/1953232

 

Note: The Roadmap can only display sprints that were created in the same Backlog. It can not show sprints from other projects / boards.

Like Markus K likes this