Hi, I am looking for some information. We have two-week sprints in our project. Team commits User stories and the sub tasks underneath. When the burndown graph is rendered in the burndown chart, is it based on status of the user story OR is it based on status of the sub tasks? Please let me know that. Because my manager is saying, it's based-on User Story. But I am saying it's based on sub tasks underneath a story. Can someone throw some light on this? I don't see an option in settings to view this information.
By the way i am scrum master i have all the privileges, except JIRA board admin.
Hello @Vijay Kumar
Based on my experience working with Scrum boards the Sprint burndown is not based on subtasks. It is based on the parent issues transitioning to a status in the right-most column of the board.
@Trudy Claspill Thank you so much for the reply. Appreciate it.
Is there a way I can check that info in settings?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is not a configurable setting, so no, it doesn't appear in any of the settings screens.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.