Does everything have to have a story point estimate for the burndown chart to work? 

1 answer

3 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 3, 2022

Welcome to the Atlassian Community!

Burndown is a measure of what you did against what you said you would.  If you don't put an estimate on an item, there is nothing for the burndown to work with.

But, it doesn't have to be story points, you can burn down on any number you want.

Ajay _view26_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 3, 2022

Yes, as Nic mentioned, burndown could be based on Story Points, Issue Count, Remaining Time estimate etc

Like Bharathi likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events