I have my Timeline view set up by scheduled start and due dates. Is there a way to show if the Epic was completed early?
Currently I have an epic that has a due date of 12/19/24, but we completed this on 12/10/24. So, the bar will show through the 19th as that is the due date. What I am wanting is to somehow keep that date, but show on the bar that the epic was complete on the 10th.