Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Roll up dates in Advanced Roadmaps

Edited

Could someone explain to me please how roll up dates work in Jira.
I do not have start date field. Only due date field. Based on what does the system calculate rolled up dates. Could somebody explain it looking  at my rooled up dates?

image.png

1 answer

1 accepted

0 votes
Answer accepted
Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Nov 14, 2023

Hi @BenWade 

See What are roll-ups in Advanced Roadmaps? for more info.

The latest Due Date of the standard/base issue type should roll-up to the "Epic" level.

Due dates of the "Epic" issue type should roll-up to the level above (as defined in the issue hierarchy).

This looks like:

Plans - Roll-up Dates.png