Roll up dates in Advanced Roadmaps

BenWade
Contributor
November 14, 2023

Could someone explain to me please how roll up dates work in Jira.
I do not have start date field. Only due date field. Based on what does the system calculate rolled up dates. Could somebody explain it looking  at my rooled up dates?

image.png

1 answer

1 accepted

0 votes
Answer accepted
Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 14, 2023

Hi @BenWade 

See What are roll-ups in Advanced Roadmaps? for more info.

The latest Due Date of the standard/base issue type should roll-up to the "Epic" level.

Due dates of the "Epic" issue type should roll-up to the level above (as defined in the issue hierarchy).

This looks like:

Plans - Roll-up Dates.png