PLEASE HELP!! Team's board has a TON of resolved stories that have been done for a very long time, but they keep rolling over to the next sprint. DONE IS THE RIGHT-MOST COLUMN.
Bigger question is - What do I do now to get these (there are hundreds) of resolved issues off of the board?
Hi @Tammy Kane
Can you please send a screenshot after hiding any confidential info?
Also do your issues have a resolution set or only status is done?
Best,
Fadoua
Thanks so much for getting back to me. Here is the board config, an example of one of the stories and a sample of the list of stories. There's nothing in the history to indicate the team is manually putting them in the current sprint. The team is saying when they complete the sprint these continue to roll-over.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Any updates here. Running into the same issue. @Tammy Kane @Fadoua
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Tammy Kane - Apologies for my delayed response. Checking at the moment ...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Tammy Kane when you close the sprint do you get any questions like do you want to move the issues to next sprint? Do you have an automation set up or a script? Something must have been done in th configuration that is why your issues keep moving to the next sprint even though they are done.
Check this old post as well please:
Is your project Company or Team one?
Best,
Fadoua
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think I got it figured. We used to have a single sprint board for multiple teams (using a query that picked issues across all teams). Recently, we created separate boards for each team with each query picking issues for that team only. However, the old board was still around, and that board didn't have all statuses mapped to the right-most column (each of of the newer team boards were configured correctly). So when we closed the sprint, some issues were rolled over because their status was not mapped to the right-most column on at least one (i.e. the older) board.